A. Purpose and Applicability.

1. Purpose: The purpose of this chapter is to provide planning, engineering and design standards for public and private transportation facilities and utilities. This Chapter is also intended to implement the City’s Transportation System Plan.

2. When Standards Apply: Unless otherwise provided, the standard specifications for construction, reconstruction or repair of transportation facilities, utilities and other public improvements within the City shall occur in accordance with the standards of and adopted under this Chapter. No development may occur unless the public facilities related to development comply with the public facility requirements established and adopted under this Chapter.

3. Standard Specifications: The City Engineer shall establish engineering standards and construction specifications consistent with the design standards of this Chapter and application of engineering principles (the “”Engineering Standards”). The Engineering Standards are incorporated in this Chapter by reference and apply as if fully set forth in this Chapter.

4. Conditions of Development Approval: No development may occur unless required public facilities are in place or guaranteed, in conformance with the provisions of this Title and the Engineering Standards. Improvements required as a condition of development approval, when not voluntarily accepted by the applicant, shall be roughly proportional to the impact of development. Findings in the development approval shall indicate how the required improvements are roughly proportional to the impact.

B. Transportation Standards.

1. Development Standards: No development shall occur unless the development has frontage or approved access to a public street, in conformance with the Access and Circulation standards of this chapter. The development shall comply with the Engineering Standards and the following standards:

a. Streets within or adjacent to a development shall be improved in accordance with Transportation System Plan and the provisions of this chapter.

b. Development of new streets, and additional street width or improvements planned as a portion of an existing street, shall be improved in accordance with this section, and public streets shall be dedicated to the applicable city, county, or state jurisdiction;

c. New streets and drives street shall be hard-surfaced; and

d. The City may accept a future improvement guarantee (e.g., owner agrees not to remonstrate [object] against the formation of a local improvement district in the future) in lieu of street improvements if one (1) or more of the following conditions exist:

1. A partial improvement may create a potential safety hazard to motorists or pedestrians;

2. Due to the developed condition of adjacent properties it is unlikely that street improvements would be extended in the foreseeable future and the improvement associated with the project under review does not, by itself, provide increased street safety or capacity, or improved pedestrian circulation;

3. The improvement would be in conflict with an adopted capital improvement plan; or

4. The improvement is associated with an approved land partition on property zoned residential and the proposed land partition does not create any new streets.

2. Modifications: A modification to the street design standards in this section and the Transportation System Plan may be granted by the City Engineer under this provision if a required improvement is not feasible due to topographic constraints or constraints posed by sensitive lands (e.g., wetlands, significant trees and shrubs) or if necessary for safety or improved function of the transportation facility.

3. Creation of Rights-of-Way for Streets and Related Purposes: Streets shall be created through the approval and recording of a final subdivision or partition plat; except the City may approve the creation of a street by acceptance of a deed, provided that the street is deemed essential by the City Council for the purpose of implementing the Transportation System Plan, and the deeded right-of-way conforms to the standards of this code. All deeds of dedication shall be in a form prescribed by the City Attorney and shall name “the public," as grantee.

4. Creation of Access Easements: The City may approve an access easement established by deed when the easement is necessary to provide for access and circulation in conformance with Vehicular Access and Circulation, Section 16.12.020 and/or Pedestrian Access and Circulation, Section 16.12.030. Access easements shall be created and maintained in accordance with the Uniform Fire Code Section 10.207.

5. Street Location, Width, and Grade: Except as noted below, the location, width, and grade of all streets shall conform to the Transportation System Plan, as applicable; and an approved street plan or subdivision plat. Street location, width and grade shall be determined in relation to existing and planned streets, topographic conditions, public convenience and safety, and in appropriate relation to the proposed use of the land to be served by such streets, including the following:

a. Street grades shall be approved by the City Engineer in accordance with the City’s engineering standards; and

b. Where the location of a street is not shown in an existing street plan, the location of streets in a development shall either:

1. Provide for the continuation and connection of existing streets in the surrounding areas, conforming to the street standards of this chapter; or

2. Conform to a street plan adopted by the City Council, if it is impractical to connect with existing street patterns because of particular topographical or other existing conditions of the land. Such a plan shall be based on the type of land use to be served, the volume of traffic, the capacity of adjoining streets, and the need for public convenience and safety.

6. Minimum Rights-of-Way and Street Sections: Street rights-of-way and improvements shall be consistent with the widths shown in Figures 16.12-A through 16.12 G. A modification shall be required in conformance with Section 2 (above) to vary from these standards. Where a range of width is indicated, the width shall be determined by the decision-making authority based upon the following factors:

a. Street classification in the Transportation System Plan;

b. Anticipated traffic generation;

c. On-street parking needs;

d. Sidewalk and bikeway requirements based on anticipated level of use;

e. Requirements for placement of utilities;

f. Street lighting;

g. Minimize drainage, slope, and sensitive lands impacts;

h. Street tree location, as provided for in Section 16.12.050;

i. Protection of significant vegetation, as provided for in Section 16.12.040;

j. Safety and comfort for motorists, bicyclists, and pedestrians;

k. Street furnishings (e.g., benches, lighting, bus shelters, etc.), when provided;

l. Access needs for emergency vehicles; and

m. Transition between different street widths (i.e., existing streets and new streets), as applicable.

7. Traffic Signals and Traffic Calming Features:

a. Traffic-calming features, such as traffic circles, curb extensions, narrow residential streets, and special paving may be used to slow traffic in neighborhoods and areas with high pedestrian traffic.

b. Traffic signals shall be required with development when traffic signal warrants are met, in conformance with the Highway Capacity Manual. The location of traffic signals shall be noted on approved street plans. Where a proposed street intersection will result in an immediate need for a traffic signal, a signal meeting approved specifications shall be installed. The developer’s cost and the timing of improvements shall be included as a condition of development approval.

8. Future Street Plan and Extension of Streets:

a. Where required by Section 16.12.020(K)(1) a Future Street Plan shall be filed by the applicant in conjunction with an application for a subdivision or partition in order to facilitate orderly development of the street system.

b. Streets shall be extended to the boundary lines of the parcel or tract to be developed, when the City Engineer determines that the extension is necessary to give street access to, or permit a satisfactory future division of, adjoining land. The point where the streets temporarily end shall conform to subsections (1)-(3), below:

1. These extended streets or street stubs to adjoining properties are not considered to be cul-de-sacs since they are intended to continue as through streets when the adjoining property is developed.

2. A barricade (e.g., fence, bollards, boulders, or similar vehicle barrier) shall be constructed at the end of the street by the subdivider and shall not be removed until authorized by the City or other applicable agency with jurisdiction over the street. The cost of the barricade shall be included in the street construction cost.

3. Temporary turnarounds (e.g., hammerhead or bulb-shaped configuration) shall be constructed for stub streets over 150 feet in length.

9. Street Alignment and Connections:

a. Staggering of streets making “T” intersections at collectors and arterials shall not be designed so that jogs of less than 300 feet on such streets are created, as measured from the centerline of the street.

b. Spacing between local street intersections shall be regulated by the Transportation Systems Plan, except where more closely spaced intersections are designed to provide an open space, pocket park, common area, or similar neighborhood amenity. This standard applies to four-way and three-way (off-set) intersections.

c. All local and collector streets that abut a development site shall be extended within the site to provide through circulation unless prevented by environmental or topographical constraints, existing development patterns or compliance with other standards in this code. This exception applies when it is not possible to redesign or reconfigure the street pattern to provide required extensions. Land is considered topographically constrained if the slope is greater than fifteen percent (15%) for a distance of 250 feet or more. In the case of environmental or topographical constraints, the mere presence of a constraint is not sufficient to show that a street connection is not possible. The applicant must show why the environmental or topographic constraint precludes some reasonable street connection.

d. Proposed streets or street extensions shall be located to provide direct access to existing or planned commercial services and other neighborhood facilities, such as schools, shopping areas, and parks.

e. In order to promote efficient vehicular and pedestrian circulation throughout the City, the design of subdivisions and alignment of new streets shall conform to the following standards in section 16.12.020 Vehicular Access and Circulation. The maximum block length shall not exceed:

1. Four hundred (400) feet length and 1,200 feet perimeter in the Central Business District;

2. Six hundred (600) feet length and 1,600 feet perimeter in residential zones (R-1, R-2, and R-3);

3. Not applicable to the Industrial zone (I); and

4. Eight hundred (800) feet length and 2,000 feet perimeter in all other zones.

Exceptions to the above standards may be granted by the City Engineer when a pedestrian access way is provided at or near mid-block, in conformance with the provisions of Section 16.12.040.

10. Sidewalks, Planter Strips, Bicycle Lanes: Sidewalks, planter strips, and bicycle lanes shall be installed in conformance with the standards in Figures 16.12-A through 16.12-E, applicable provisions of the Transportation System Plan, the Comprehensive Plan, street connectivity plan, and adopted future street plans. Maintenance of sidewalks, curbs, and planter strips is the continuing obligation of the adjacent property owner.

11. Intersection Angles: Streets shall be laid out so as to intersect at an angle as near to a right angle as practicable, except where topography requires a lesser angle or where a reduced angle is necessary to provide an open space, pocket park, common area, or similar neighborhood amenity.

12. Existing Rights-of-Way: Whenever existing rights-of-way adjacent to or within a tract are of less than standard width, additional rights-of-way shall be provided at the time of subdivision or development, subject to the provision of Section 16.12.050(A).

13. Cul-de-sacs: A dead-end street shall be no more than 200 feet long and shall only be used when environmental or topographical constraints, existing development patterns, or compliance with other standards in this code preclude street extension and through circulation.

a. All cul-de-sacs shall terminate with a circular or hammer-head turnaround. Circular turnarounds shall have a minimum radius of forty-two (42) feet, (i.e., from center to edge of pavement); except that turnarounds may be larger when they contain a landscaped island or parking bay in their center. When an island or parking bay is provided, there shall be a fire apparatus lane of twenty (20) feet in width; and

b. The length of the cul-de-sac shall be measured along the centerline of the roadway from the near side of the intersecting street to the farthest point of the cul-de-sac.

14. This section intentionally left blank.

15. Curbs, Curb Cuts, Ramps, and Driveway approaches: Concrete curbs, curb cuts, wheelchair, bicycle ramps and driveway approaches shall be constructed in accordance with standards specified in Sections 16.12.020 and 16.12.030.

16. Streets Adjacent to Railroad Right-of-Way: Wherever the proposed development contains or is adjacent to a railroad right-of-way, a street approximately parallel to and on each side of such right-of-way at a distance suitable for the appropriate use of the land shall be created. New railroad crossings and modifications to existing crossings are subject to review and approval by Oregon Department of Transportation.

17. Development Adjoining Arterial Streets: Where a development adjoins or is crossed by an existing or proposed arterial street, the development design shall separate residential access and through traffic, and shall minimize traffic conflicts. The design shall include one (1) or more of the following:

a. A parallel access street along the arterial with a landscape buffer separating the two (2) streets;

b. Deep lots abutting the arterial or major collector to provide adequate buffering with frontage along another street. Double-frontage lots shall conform to the buffering standards in Chapter 16.12.020;

c. Screen planting at the rear or side property line to be contained in a non-access reservation (e.g., public easement or tract) along the arterial; or

d. Other treatment suitable to meet the objectives of this subsection;

e. If a lot has access to two (2) streets with different classifications, primary access shall be from the lower classification street, in conformance with Section 16.12.020.

18. Alleys, Public or Private. Alleys shall conform to the standards in the Transportation System Plan. While alley intersections and sharp changes in alignment shall be avoided, the corners of necessary alley intersections shall have a radius of not less than twelve (12) feet.

19. Private Streets: Private streets shall not be used to avoid connections with public streets. Gated communities shall be prohibited when they block street connections that are outlined in the Transportation Systems Plan street connectivity plan. Design standards for private streets shall conform to the provisions of Table 16.12-A.

20. Street Names: No street name shall be used that will duplicate or be confused with the names of existing streets in the City or Urban Growth Area, except for extensions of existing streets. Street names, signs, and numbers shall conform to the established pattern in the surrounding area, except as requested by emergency service providers and the City Charter.

21. Survey Monuments: Upon completion of a street improvement and prior to acceptance by the City, it shall be the responsibility of the developer’s registered professional land surveyor to provide certification to the City that all boundary and interior monuments shall be reestablished and protected.

22. Street Signs: The city, county, or state with jurisdiction shall install all signs for traffic control and street names. The cost of signs required for new development shall be the responsibility of the developer. Street name signs shall be installed at all street intersections. Stop signs and other signs may be required.

23. Mail Boxes: Plans for mail boxes to be used shall be approved by the United States Postal Service.

24. Street Light Standards: Street lights shall be installed in accordance with City standards and shielded in a downward pattern.

25. Street Cross-Sections: The final lift of asphalt or concrete pavement shall be placed on all new constructed public roadways prior to final City acceptance of the roadway and within one (1) year of the conditional acceptance of the roadway unless otherwise approved by the City Engineer.

C. Public Use Areas.

1. Dedication Requirements:

a. Where a proposed park, playground, or other public use shown in a plan adopted by the City or the Hood River Valley Parks and Recreation District is located in whole or in part in a subdivision, the City may require the dedication or reservation of this area on the final plat for the subdivision.

b. Where an adopted plan of the City does not indicate proposed public use areas, the City may require the dedication or reservation of areas within the subdivision of a character, extent, and location suitable for the development of parks and other public uses if:

1. Approved by the Hood River Valley Parks and Recreation District; and,

2. Determined by the Planning Commission to be in the public interest in accordance with adopted Comprehensive Plan policies.

c. All required dedications of public use areas shall conform to Section 16.12.060(A)(4) (Conditions of Approval).

2. System Development Charge Credit: If authorized by the Hood River Valley Parks and Recreation District, dedication of land to the City for public use areas shall be eligible as a credit toward any required system development charge for parks.

D. Sanitary Sewer and Water Service Improvements.

1. Sewers and Water Mains Required. Sanitary sewers and water mains shall be installed to serve each new development and to connect developments to existing mains in accordance with the City’s construction specifications and the applicable Comprehensive Plan policies.

2. Sewer and Water Plan Approval: Development permits for sewer and water improvements shall not be issued until the City Engineer has approved all sanitary sewer and water plans in conformance with City standards.

3. Over-sizing: Proposed sewer and water systems shall be sized to accommodate additional development within the area as projected by the Comprehensive Plan. The developer shall be entitled to system development charge credits for the over-sizing.

4. Permits Denied: Development permits may be restricted by the City where a deficiency exists in the existing water or sewer system which cannot be rectified by the development, and which if not rectified, will result in a threat to public health or safety, surcharging of existing mains, or violations of state or federal standards pertaining to operation of domestic water and sewerage treatment systems. Building moratoriums shall conform to the criteria and procedures contained in ORS 197.505.

E. Storm Drainage.

1. General Provisions: The City shall issue a development permit only where adequate provisions for storm water and flood water runoff have been made in accordance with the requirements of the City Engineer.

2. Accommodation of Upstream Drainage: Culverts and other drainage facilities shall be large enough to accommodate potential runoff from the entire upstream drainage area, whether inside or outside the development. Such facilities shall be subject to review and approval by the City Engineer.

3. Effect on Downstream Drainage: Where it is anticipated by the City Engineer that the additional runoff resulting from the development will overload an existing drainage facility, the City shall withhold approval of the development until provisions have been made for improvement of the potential condition or until provisions have been made for storage of additional runoff caused by the development in accordance with City standards.

F. Utilities.

1. Underground Utilities: All utility lines including, but not limited to, those required for electric, communication, lighting and cable television services, and related facilities shall be placed underground, except for surface mounted transformers, surface mounted connection boxes and meter cabinets which may be placed above ground, temporary utility service facilities during construction, and high capacity electric lines operating at 50,000 volts or above. The following additional standards apply to all new subdivisions, in order to facilitate underground placement of utilities:

a. The developer shall make all necessary arrangements with the serving utility to provide the underground services. Care shall be taken to ensure that all above ground equipment does not obstruct vision clearance areas for vehicular traffic (See Section 17.04.090);

b. The City reserves the right to approve the location of all surface mounted facilities;

c. All underground utilities, including sanitary sewers and storm drains installed in streets by the developer, shall be constructed prior to the surfacing of the streets; and

d. Stubs for service connections shall be long enough to avoid disturbing the street improvements when service connections are made.

2. Easements: Easements shall be provided for all underground utility facilities.

3. Exception to Under-Grounding Requirement: The standard applies only to proposed subdivisions. An exception to the under-grounding requirement may be granted due to physical constraints, such as steep topography, sensitive lands, or existing development conditions.

G. Easements. Easements for sewers, storm drainage and water quality facilities, water mains, electric lines, or other public utilities shall be dedicated on a final plat, or provided for in the deed restrictions. The developer or applicant shall make arrangements with the City, the applicable district, and each utility franchise for the provision and dedication of utility easements necessary to provide full services to the development. The City’s standard width for public main line utility easements shall be fifteen (15) feet unless otherwise specified by the utility company, applicable district, or City Engineer.

H. Construction Plan Approval and Assurances. A construction site permit is required for all public and private improvements subject to this title. No public or private improvements, including sanitary sewers, storm sewers, streets, sidewalks, curbs, lighting, parks, or other requirements shall be undertaken except after the plans have been approved by the City, permit fee paid, and permit issued. The permit fee is required to defray the cost and expenses incurred by the City for design reviews, construction observation and other services in connection with the improvement. The permit fee shall be set by City Council resolution. The City may require the developer or subdivider to provide bonding or other performance guarantees and warranties to ensure completion and performance of required public improvements.

I. Installation.

1. Conformance Required: Improvements installed by the developer either as a requirement of these regulations or at their own option, shall conform to the requirements of this chapter, approved construction plans, and to improvement standards and specifications adopted by the City.

2. Adopted Installation Standards: The Oregon Standard Specifications for Construction, Oregon Department of Transportation and Oregon Chapter A.P.W.A., shall be a part of the City’s adopted installation standard(s); other standards may also be required upon recommendation of the City Engineer.

3. Commencement: Work shall not begin until the City has been notified in advance.

4. Resumption: If work is discontinued for more than one (1) month, it shall not be resumed until the City is notified.

5. Construction Observation: Improvements shall be constructed under the observation and to the satisfaction of the City. The City may require minor changes in typical sections and details if unusual conditions arising during construction warrant such changes in the public interest. Modifications requested by the developer shall be subject to land use review under Modifications and Extensions, Section 16.08. Any monuments that are disturbed before all improvements are completed by the subdivider shall be replaced by an Oregon Licensed Land Surveyor prior to final acceptance of the improvements.

6. Engineer’s Certification and As-Built Plans: A civil engineer registered in the state of Oregon shall provide written certification in a form required by the City that all improvements, workmanship, and materials are in accord with current and standard engineering and construction practices, conform to approved plans and conditions of approval, and are of high grade, prior to City acceptance of the public improvements, or any portion thereof, for operation and maintenance. The developer’s engineer shall also provide two (2) sets of “as-built” drawings, in conformance with the City Engineer’s specifications, for permanent filing with the City. One set shall be a hard copy plot or print and one set shall be in electronic AutoCad format compatible with the City’s computer hardware and software. (Ord. 2062 §2 (Exh. B), 2021)